Yanhua Module 39 Installation Guide for Benz HU7 Instrument

Yanhua ACDP Module 39 is equipped with two kinds of interface boards, one MQB V2 Adapter, and one MB HU7 Instrument Module Emulator. This guide will walk you through the installation process of the interface board and emulator for Mercedes-Benz HU7 instrument module (A206/A223/A 177) with chip model R7F7015293/ R7F7015294.

yanhua module 39 and benz hu7 installation 1

 

PART 1: Install interface board for mileage correction

PART 2: Install emulator after mileage correction

 

PART 1: Install interface board for mileage correction

How to choose Yanhua Module 39 Interface Board for different instrument types?

1.Yanhua BENZ-HU7-A R7F7015293 Interface Board:

For BENZ HU7 A223, A206, A177 dashboard types with R7F7015293 chip below.

yanhua module 39 and benz hu7 installation 2

 

  • For BENZ HU7 A223, A206 dashboard types (set the DIP switch on the BENZ-HU7-A interface board to the A- end)

yanhua module 39 and benz hu7 installation 3

 

  • For BENZ HU7 A177 dashboard type (set the DIP switch on the BENZ-HU7-A interface board to the C- end)

yanhua module 39 and benz hu7 installation 4

 

2.Yanhua BENZ-HU7-B R7F7015294 Interface Board:

For BENZ HU7 A223 dashboard type with R7F7015294 chip below

yanhua module 39 and benz hu7 installation 5

yanhua module 39 and benz hu7 installation 6

 

Yanhua Module 39 Interface Board Installation Guide:

1.For Yanhua BENZ-HU7-A R7F7015293 Interface Board

Requirement:

  • Yanhua ACDP2
  • BENZ-HU7-A R7F7015293 Interface Board
  • MQB V2 Adapter
  • 20 PIN cable
  • BENZ HU7 A223/ A206 dashboard module with R7F7015293 chip

yanhua module 39 and benz hu7 installation 7

 

Step 1:

Push the latch on the interface board to the unlock position. Then, identify the correct installation area on the instrument based on the positioning pillars of the interface board.

Step 2:

Move the DIP switch on the BENZ-HU7-A Interface Board to the A-end position.

Step 3:

Locate the correct positioning holes for D1 – D4 on the meter.

Step 4:

Verify the test point pin definitions.

Step 5:

Align the positioning posts on the interface board and the D2 positioning pins with the corresponding positioning holes on the instrument.

Step 6:

Press down on the interface board and then push the PCB lock buckle to the locked position to secure the interface board in place. The installation is now complete.

yanhua module 39 and benz hu7 installation 8

yanhua module 39 and benz hu7 installation 9

yanhua module 39 and benz hu7 installation 10

yanhua module 39 and benz hu7 installation 11

yanhua module 39 and benz hu7 installation 12

yanhua module 39 and benz hu7 installation 13

 

BENZ-HU7-A R7F7015293 Interface Board Overall Connection Diagram

yanhua module 39 and benz hu7 installation 14

 

Note:

The Benz HU7 A177 installation steps are the same as A223/ A206.

The only differences are step 2 and step 4.

For A177 dashboard module:

yanhua module 39 and benz hu7 installation 15

yanhua module 39 and benz hu7 installation 16

 

2.For Yanhua BENZ-HU7- B R7F7015294 Interface Board

Requirement:

  • Yanhua Mini ACDP2
  • BENZ-HU7-B R7F7015294 Interface Board
  • MQB V2 Adapter
  • 20 PIN cable
  • BENZ HU7 A223 dashboard module with R7F7015294 chip

yanhua module 39 and benz hu7 installation 17

 

Step 1:

Push the latch of the interface board to the unlock position and determine its installation area on the instrument according to the positioning pillars of the interface board.

Step 2:

Find the correct positioning holes of D1 – D4 of the meter.

Step 3:

Check the test point pin definition

Step 4:

Align the positioning posts of the interface board and the D2 positioning pins with the positioning holes of the instrument.

Step 5:

Press down on the interface board, push the PCB lock buckle to the Locked position to lock the interface board, installation is done.

yanhua module 39 and benz hu7 installation 18

yanhua module 39 and benz hu7 installation 19

yanhua module 39 and benz hu7 installation 20

yanhua module 39 and benz hu7 installation 21

yanhua module 39 and benz hu7 installation 22

yanhua module 39 and benz hu7 installation 23

 

PART 2: Install emulator after mileage correction

The Yanhua MB HU7 Instrument Module Emulator is designed to prevent black screen issues on the dashboard. It must be permanently soldered into the vehicle and is intended for one-time use—each vehicle requires its own emulator, and it cannot be reused.

After modifying the mileage by Mini ACDP2, proceed to solder the HU7 Emulator as shown below:

Check wire colors (black, red, green, blue, white) for correct pinouts.

yanhua module 39 and benz hu7 installation 24

 

The overall connection diagram:

yanhua module 39 and benz hu7 installation 25

 

Learn more:

Yanhua Module 39 Correct Benz MB HU7 Instrument Mileage

(Visited 145 times, 1 visits today)
Share